Offshore
Publication of completion dates in accordance with § 17d paragraph 2 sentence 3 of the German Energy Act (EnWG)
Expected completion dates
Grid connection system | Project | Areas to be connected | Estimated completion date |
---|---|---|---|
NOR-3-2 | DolWin4 | N-3.5 ; N-3.6 |
31.08.2028 |
NOR-6-3 | BorWin4 | N-6.6 ; N-6.7 |
16.11.2028 |
NOR-9-1 | BalWin1 | N-9.1 |
16.09.2030 |
NOR-10-1 |
BalWin2 | N-10.1 | 15.09.2031 |