Tendering Procedure of Grid Losses for delivery period 2013

The yearly amount of grid losses of Amprion which is procured by tender procedures is structured into particular lots for each delivery period. A tender includes several identical lots of a commercial stock exchange product. (Base Year or Peak Year or Base Quarter or Peak Quarter)

The call and acceptance of tender takes place on the internet plattform www.tso-grid-loss.net (only registered user).

A short overview and instruction for the internet plattform can be found on our website.

According to the specification of the Bundesnetzagentur Amprion will provide all information in terms of number of lots, amount of energy and structure of each lot three weeks before each tender date at the latest.

The current tender procedures take place on:

*) related to the delivery period 2013

tender date period of submission structure
of the lot*
number
of lots
delivery
rate
per lot
(MW)
ammount of energie
per lot
(MWh)
The procurement for the delivery year 2013 is completed

Documents for the delivery period on 2013

Excel-file of the profile (XLS | 2.2 MB)

The general terms and conditions for tender participation including information concerning products, bid placement and award procedure can be found on our website. Furthermore please find on our website a draft of the electricity supply contract (Stromliefervertrag) to be used.

A prerequisite for participating in the call for tender process is the existence of a valid balance group or subgroup of the participant in the Amprion control area. Participants must be registered on the internet plattform. Insofar the participant is not a balance responsible entity himself the participant has to bring forward a document in which the balance responsible entity obligates himself to the full extent towards the participant to handle the delivery of the loss energy to Amprion via his balancing group. The delivery has to be carried out according to the balancing group contract concluded between the balance responsible entity and Amprion.

To participate in the tendering, we would kindly ask you to register once. For registration please use the registration sheet downloadable on our website.

If you have any questions please contact us using the following e-mail address with reference to "Tender grid losses”:

E-Mail to Amprion

Past tenders and results:

*) of the awarded offers

tender date period of submission structure
of the lot
number
of lots
delivery
rate
per lot
(MW)
ammount of energie
per lot
(MWh)
average price (€/MWh) maximum price* (€/MWh)
11/10/2011 11/10/2011
05 till 11 a.m.
Base-Year 8 1 8760 55.39 55.39
14/10/2011 14/10/2011
05 till 11 a.m.
Base-Year 6 1 8760 55.14 55.15
18/10/2011 18/10/2011
05 till 11 a.m.
Base-Year 8 1 8760 54.58 54.59
20/10/2011 20/10/2011
05 till 11 a.m.
Base-Year 6 1 8760 54.40 54.40
03/11/2011 03/11/2011
05 till 11 a.m.
Base-Year 8 1 8760 54.38 54.38
08/11/2011 08/11/2011
05 till 11 a.m.
Base-Year 8 1 8760 55.93 55.93
15/11/2011 15/11/2011
05 till 11 a.m.
Base-Year 8 1 8760 55.40 55.40
25/11/2011 25/11/2011
05 till 11 a.m.
Base-Year 6 1 8760 53.44 53.44
01/12/2011 01/12/2011
05 till 11 a.m.
Base-Year 8 1 8760 53.44 53.44
06/12/2011 06/12/2011
05 till 11 a.m.
Base-Year 6 1 8760 52.41 52.43
15/12/2011 15/12/2011
05 till 11 a.m.
Base-Year 8 1 8760 53.33 53.34
21/12/2011 21/12/2011
05 till 11 a.m.
Base-Year 8 1 8760 53.67 53.68
11/01/2012 11/01/2012
05 till 11 a.m.
Base-Year 8 1 8760 51.79 51.80
17/01/2012 17/01/2012
05 till 11 a.m.
Base-Year 8 1 8760 50.48 50.49
25/01/2012 25/01/2012
05 till 11 a.m.
Base-Year 8 1 8760 51.29 51.29
02/02/2012 02/02/2012
05 till 11 a.m.
Peak-Year 7 2 6264 65.67 65.88
09/02/2012 09/02/2012
05 till 11 a.m.
Base-Year 8 1 8760 52.32 52.34
14/02/2012 14/02/2012
05 till 11 a.m.
Base-Year 8 1 8760 51.11 51.12
24/02/2012 24/02/2012
05 till 11 a.m.
Peak-Year 7 2 6264 65.86 65.90
28/02/2012 28/02/2012
05 till 11 a.m.
Base-Q1 10 3 6477 58.03 58.04
08/03/2012 08/03/2012
05 till 11 a.m.
Base-Year 6 1 8760 52.77 52.77
14/03/2012 14/03/2012
05 till 11 a.m.
Base-Q1 10 3 6477 56.99 57.00
20/03/2012 20/03/2012
05 till 11 a.m.
Peak-Q1 4 3 2304 70.64 70.65
26/03/2012 26/03/2012
05 till 11 a.m.
Base-Q1 10 3 6477 55.66 55.80
03/04/2012 03/04/2012
05 till 11 a.m.
Base-Year 10 1 8760 51.37 51.38
11/04/2012 11/04/2012
05 till 11 a.m.
Peak-Q1 5 3 2304 69.95 69.99
17/04/2012 17/04/2012
05 till 11 a.m.
Peak-Q2 5 3 2340 55.50 55.63
26/04/2012 26/04/2012
05 till 11 a.m.
Base-Year 10 1 8760 50.45 50.47
03/05/2012 03/05/2012
05 till 11 a.m.
Peak-Q2 5 3 2340 54.35 54.35
10/05/2012 10/05/2012
05 till 11 a.m.
Base-Year 8 1 8760 49.79 49.79
15/05/2012 15/05/2012
05 till 11 a.m.
Base-Q3 2 1 2208 45.10 45.10
23/05/2012 23/05/2012
05 till 11 a.m.
Base-Q4 8 3 6627 53.54 53.57
31/05/2012 31/05/2012
05 till 11 a.m.
Base-Year 8 1 8760 49.09 49.09
05/06/2012 05/06/2012,
05 till 11 a.m.
Base-Q4 8 3 6627 53.27 53.29
15/06/2012 15/06/2012,
05 till 11 a.m.
Base-Year 9 1 8760 47.86 47.87
20/06/2012 20/06/2012,
05 till 11 a.m.
Base-Q4 8 4 8836 52.15 52.15
26/06/2012 26/06/2012,
05 till 11 a.m.
Peak-Q4 4 2 1584 67.11 67.30

NB: Amprion reserves the right to amend and update all published information as and when necessary.

The German documents – especially the electricity supply contract – are the legally binding documents. The English documents and the English website are provided for convenience of reading only.

Registration sheet (XLS | 38 KB)

General terms and conditions grid losses (PDF | 45 KB)

Electricity supply contract in German (Stromliefervertrag) for year of delivery: 2013 (PDF | 133 KB)

Instruction for the internet plattform tso-grid-loss.net (PDF | 1.4 MB) 
 

back